FAT
Also: Factory Acceptance Test, Factory-Acceptance-Test, Werksabnahme, Werksabnahmetest, FAT-Test
AI-generated
The Factory Acceptance Test (FAT) is a formal acceptance test in which a system or installation is checked at the manufacturer's site for functionality, completeness, and contractual compliance. It is considered a central milestone in the procurement project before the system is delivered to the operator.
Key facts
- The FAT takes place at the manufacturer's site and verifies that a system meets the contractually agreed requirements before it is delivered to the operator.
- A test plan agreed in advance with clear acceptance criteria is the most important prerequisite for a smooth FAT.
- Deviations are documented in a defect report or punch list and must be resolved before or at the latest during the SAT.
- The FAT reduces the risk of defects being discovered only after commissioning at the operator's site — which is typically far more costly to address.
What is a FAT?
The Factory Acceptance Test (FAT) refers to a structured acceptance test carried out at the manufacturer's or system integrator's site — before the system is transported to the future operator. The goal is to demonstrate, under controlled conditions, that the delivered solution meets the contractually agreed requirements. In intralogistics, the FAT is particularly relevant when procuring conveyor systems, automated storage systems, sorters, or WMS implementations.
At its core, the FAT documents the transition point from manufacturer responsibility to joint acceptance: the client and the manufacturer work through a predefined test plan together to verify that functions, interfaces, and performance parameters have been implemented as agreed. Deviations are recorded, classified, and documented in a defect report.
How does a FAT work in practice?
A FAT is typically structured in several phases. First, a test plan is created that defines all scenarios to be tested, acceptance criteria, and test responsibilities. Ideally, this plan should be anchored in the contract to avoid disputes at a later stage.
During execution, test cases are worked through step by step. Common test items in intralogistics include:
- Functional testing of individual components (e.g. conveyor technology, warehouse management software, scanners)
- Simulation of operational scenarios and exception situations (e.g. fault conditions, emergency shutdown)
- Testing of interfaces to ERP or WMS systems
- Verification of throughput and performance parameters
- Documentation review (manuals, circuit diagrams, safety certifications)
Identified deviations are classified — commonly by severity (e.g. critical, major, minor). The FAT is only considered passed once agreed minimum requirements have been met. Open items are recorded in a punch list and must be resolved before or at the latest during the SAT (Site Acceptance Test) at the operator's site.
What matters when planning a FAT?
A common mistake is defining the test plan only shortly before the FAT date. The earlier acceptance criteria are fixed in writing, the less room for interpretation remains during the acceptance process. In addition, all relevant stakeholders — logistics planning, IT, procurement, and any external consultants — should be involved in the FAT, as decisions on deviations often need to be made on the spot.
Whether a FAT is mandatory depends on the contract. For complex or safety-critical systems, however, it is standard industry practice and significantly reduces the risk of costly rework after commissioning. The scope and degree of formalization vary greatly depending on the vendor — which is why precise contractual specification is recommended.
Related terms
- Abnahmeprozess (FAT/SAT)
The acceptance process (FAT/SAT) comprises two consecutive test phases used to verify that intralogistics systems comply with contractual requirements before commissioning.
- Ausschreibungsmanagement Logistik
Logistics tender management refers to the structured overall process by which companies solicit bids for logistics services or systems on the market, make offers comparable, and prepare a well-founded award decision.
- Automatisierung
Automation refers to the use of technologies and systems to execute processes fully or partially without human intervention. In intralogistics, the spectrum ranges from simple conveyor systems to fully automated high-bay warehouses with autonomous vehicles.
- Brownfield Logistik
Brownfield logistics refers to the modernization, expansion, or restructuring of existing warehouse and logistics sites during ongoing operations. In contrast to the greenfield approach, it involves working with existing building structures, infrastructure, and technology.
- Business Case Automatisierung
The Business Case Automation evaluates, from an economic and operational perspective, whether an investment in warehouse or intralogistics automation is justified. It summarizes costs, benefits, risks, and assumptions in a structured way, forming the basis for management approval decisions.